Olympic Dam Copper-Uranium Mine, Adelaide, Australia

The Olympic Dam copper-uranium mine and plant is situated in South Australia, 580km north-west of Adelaide. Opened in 1988, Olympic Dam is wholly owned and operated by WMC Resources, which discovered the deposit in 1975. A A$1,940m expansion programme was completed in 1999, raising its capacity to 200,000t/y of copper and 4,300t/y of uranium, plus gold and silver. In mid-2005, BHP Billiton gained control of WMC Resources in an A$9.2bn takeover.

In 2007 BHP Billiton announced that it would undertake a A$6bn–A$7bn expansion of the Olympic Dam mine. The company says that annual ore production will increase up to 70 million tonnes, a seven-fold increase if the expansion proceeds. Copper production will increase from approximately 180, 000t a year to approximately 730,000t.

This would include 500,000oz of gold, 500,000t of copper and 15,000t of yellowcake. Existing average gold production is 80,000oz pa. The additional proven reserves of uranium now make Olympic Dam one of the most promising uranium mines in the world.

Intierra's Minmet data base puts current Olympic Dam proven-probable reserves at 756 million tonnes grading 1.5% copper, 0.5kg/t U308, 0.5 g/t gold and 3.1g/t silver. The measured to inferred resources were 3.214 billion tonnes at 1.025% copper, 0.337kg/t U308, 0.442g/t gold and 2.144g/t silver. On these figures, without improved grades or increased tonnage, Olympic Dam has proven reserves of a contained 12.153Moz gold and contained resources of 45.62Moz.

The results of the study ended much speculation within the mining and investment communities, which were especially abuzz about the potential upgrade of gold reserves.

Once fully complete, the expansion would make Olympic Dam the biggest mine in the world. Concerns have naturally been voiced about how the necessary infrastructure will be funded and deployed. Finding skilled labour will be another challenge.

GEOLOGY AND RESERVES

The deposit occurs in the basement rocks of the Stuart Shelf geological province in the north of South Australia, west of Lake Torrens. Mineralisation consists of medium-grained chalcopyrite, bornite and chalcocite, fine-grained disseminated pitchblende, gold, silver and rare earth minerals that occur in a magnetic hydrothermal breccia complex beneath 350m of overburden. The ore occurs in distinct zones that determine the mine access and layout.

As of September 2008, the total ore reserves at Olympic Dam stood at 473Mt, up from 399Mt in 2007, grading 1.86% copper and 0.6kg/t U3O8..

MINING

The current scope and logistical demands of the mine will be increased by a few orders of magnitude once the expansion gets into full swing. The mine will gradually be transformed from an underground operation to open pit.

Three vertical shafts and a decline access the orebody, which is worked using a variation of sublevel open stoping. Each stope may contain 300,000t of ore. Drill drives are driven on the stope centre line and blastholes drilled in vertical rings. These are charged with ANFO and detonated with shock tube detonators. The drilling fleet comprises Atlas Copco and Tamrock production rigs, with development being carried out using two Tamrock (now Sandvik) jumbos. Atlas Copco has supplied two modified Simba H4356S production drilling rigs.

Stopes are backfilled with cemented aggregate of crushed 'mullock' (waste rock), deslimed mill tailings, cement and pulverised fuel ash (PFA). Automation has done much to reduce production costs at Olympic Dam. Innovations include the automated underground haulage system and the 'smart' loader, a robotics-driven, decision-making underground ore carrier.

ORE PROCESSING

Processing facilities consist of a copper concentrator, hydrometallurgical plant, copper smelter, sulphuric acid plant, copper and gold/silver refineries. Recent expansions included a Svedala autogenous mill, additions to the flotation sections, two counter-current decantation thickeners, an electric slag-cleaning furnace, a new anode furnace gas-cleaning plant and additional electro-refining cells.

Copper is recovered primarily by copper sulphide flotation from slurry before the copper concentrate is smelted and electro-refined to high-purity copper.

Wastes generated during electro-refining are treated to recover gold and silver. After treatment by flotation, the finely-crushed ore is leached with sulphuric acid to dissolve uranium and any remaining copper. The leach liquor is processed in the solvent extraction plant to separate the residual copper and uranium streams. Copper is recovered by electrowinning and uranium converted to yellowcake and calcined uranium oxide.

Installation of two pulsed columns has increased uranium recovery from solution from 90% to about 97%. These columns use an air pulse to mix the acidic and organic solutions, providing better contact for the chemical reaction involved in transferring the uranium from one to the other.

Copper cathode sheets are transported by truck within Australia and to Port Adelaide for export. All uranium oxide produced at Olympic Dam is exported. The gold plant became fully operational in 2000. A fire in 2002 at the solvent extraction / electrowinning plant cost over A$300m to repair, while WMC also spent A$127m on renovating the copper smelter during 2003.

EXPANSION

At the end of October 2008, BHP Billiton announced that it expects to complete the first of the mine's five-stage expansion by 2013, boosting annual production capacity to 200,000t of copper, 4,500t of uranium and 120,000oz of gold. Up to the end of the business year on 30 June 2008, Olympic Dam produced 169,000t of copper cathode, 4,144t of uranium and 80,517oz of gold.

The expansion will be followed by a staged development of an open pit, with an eventual target output of 730,000t of copper and 19,000t of uranium. The company also said it is looking at shipping copper concentrate directly to smelters in China, which will cut the cost of producing cathodes at the mine.

ENVIRONMENT

Olympic Dam maintains storage facilities for all waste products. The plant has been designed so that any spillage of ore, concentrate or process slurries can readily be returned to the process circuit. The plant also includes comprehensive air pollution control equipment and both air emissions and noise are monitored. Extensive radiation monitoring of personnel and the environment is ongoing.

The Australian and South Australian Governments jointly determined that the proposed Olympic Dam expansion must be formally assessed through an Environmental Impact Statement (EIS).

Thursday, November 27, 2008

Highland Valley Copper Mine, British Columbia, Canada


Highland Valley copper/molybdenum mine is located 75km southwest of Kamloops, British Columbia, Canada. The Valley pit has yielded more than 1,100Mt of ore in its lifetime.

Highland Valley Copper was created as a partnership between Rio Algom and Cominco in 1986 to combine the Bethlehem and Lornex mines. Following the merger between Teck and Cominco in 2001, the 2000 takeover of Rio Algom by Billiton and Billiton's subsequent merger with BHP, the mine was then majority owned by Teck Cominco (63.9%) and BHP Billiton (33.6%). At the beginning of 2004, Teck Cominco exercised its pre-emptive rights over BHP Billiton's holding when the latter put it up for sale, and is now 97.5% owner of Highland Valley.

Production at the mine has decreased significantly the last few years due to an increased reliance on the lower-grade Lornex pit in line with a $C300m mine expansion project designed to push its life expectancy out to 2019. All of the mining equipment required for this work is now on site and commissioned. Highland Valley’s total copper production for 2007 was 136,000 tons, compared to 167,000 tons for the previous year. Molybdenem was just under 4 million pounds compared with just over 4 million for 2006.


Geology and reserves

Highland Valley is a low-grade (0.4% Cu) porphyry copper-molybdenum deposit associated with the younger intrusive phases of the early to mid-jurassic, calc-alkaline Guichon Creek batholith.

As of the end of 2005, proven and probable ore reserves totalled 318Mt grading 0.43% copper and 0.008% molybdenum. Mineral resources added a further 151.9Mt at 0.37% copper and 0.005% moly.

Reserves have been drill defined at 60 to 115 metre centres and resources at 125 metre centres. In 2007, a positive geotechnical study at Lornex added 197 million tons of indicated resource at a US$1.65/lb copper price and US$9.50/lb molybdenum price.


Open-pit mining

Open-pit mining is used in both the Lornex and Valley pits, with around 90% of the ore coming from the Valley pit. Three computerised Bucyrus 49R drills prepare blast hole patterns while nine P&H 4100A 37 yd³ electric shovels load ore into a fleet of Komatsu haul trucks for transport to in-pit crushers. In 2001, eight of the 170t-capacity trucks were replaced by six new 215t haulers. Further support is given by three water trucks, eight road graders, eight tracked bulldozers, three rubber-tyred bulldozers and one front-end loader.

The mine uses two semi-mobile in-pit crushers to minimise haul distances. Several kilometres of conveyors carry up to 12,000t/h of crushed ore to three stockpiles at the Highland mill. Pit operations are monitored and controlled by a Modular Mining Systems computerised dispatch system designed to maximise mine production. In addition minute-by-minute mapping is achieved by combining GPS navigation and survey with GIS mapping techniques.


Ore processing

The Highland mill, the world’s third largest copper concentrator, was constructed in the late 1980s by combining the original Lornex and Highmont mills. The complete Highmont mill was moved by road 10km from its former site to a new position adjacent to the Lornex plant.

The crushed ore enters two grinding stages in five parallel grinding lines incorporating two fully-autogenous mills, and three semi-autogenous (SAG) mills grinding a total of 5,400t/h. The second stage consists of eight ball mills reducing ore to sand-sized particles which feed the flotation circuits. The primary flotation stage extracts copper and molybdenum from the slurry before copper and molybdenum are separated. The molybdenum concentrate is mixed with a leaching brine in sealed, pressurised, heated vessels where residual copper is dissolved, leaving a high-grade molybdenum concentrate. Lastly, the copper and molybdenum concentrates are filtered and dried in gas-fired driers for shipping. Three 1m-diameter pipelines take the tailings 7km overland from the mill to the Valley tailings pond.


Concentrate transport

Copper concentrate is transported in bulk 40km to the rail yard at Ashcroft, then by rail to north Vancouver and finally by ship to overseas smelters. The molybdenum concentrate is packaged on site for shipment.




Environment

In 1997, Highland Valley Copper was presented with the 1996 British Columbia Reclamation Citation Award in the metal mining category for its outstanding achievement in reclaiming 1,000ha and planting 700,000 native trees and shrubs. Work to establish fish stocks in different water bodies on the property is continuing to be successful.



Production

As noted in the overview above, production at Highland Valley has declined significantly the last few years. Teck Cominco recently downgraded its production guidance for the 2008 full year from an initial 122,000 tons to 113,000 tons. Highland Valley’s total copper production for 2007 was 136,000 tons, compared to 167,000 tons for the previous year. Molybdenem was just under 4 million pounds compared with just over 4 million for 2006. Total ore mined fell also to 42.6Mt.
Teck Cominco has stated that mining of areas with higher clay content will continue throughout 2008 and 2009. Just over half of the total ore mined for Q3 2008 came from the lower grade Lornex mine compared with only 41% for the 5% to 30,500 tons.


The future

Waste stripping for Highland Valley's $C300m mine life extension is continuing with the pushback of the east wall in the Valley pit progressing well despite a minor geotechnical failure in the third quarter which is currently being rectified.

All the equipment is on site, permits received and contractors arranged. The pushback of the west wall necessary to extend the mine life to 2019 is scheduled to commence in early 2009 after the mine permit amendment received.